Inverness Airport [Station]

A portion of new platform is lowered at Inverness Airport station.

Network Rail has announced that a section of the line between Inverness and Aberdeen will be closed for eleven days to enable work on the Inverness Airport station programme.

Engineers will work around the clock during this time to carry out extensive work between Inverness and Nairn as part of the wider programme of enhancements being delivered around the new station development.

Over a period of 11 days from 23.55 Friday 14th October until the 04.45 on Wednesday 26th October, work will be continuous to substantially complete the new Airport station, to install the passing loop through the station and to enhance sections of track within the area.

Location: Inverness Airport [Station]

Original line: Inverness and Nairn Railway

Photographer: Network Rail

Contact photographer: Network Rail

Contact editor

Date: 29/09/2022

Image number: 82688


Other photographs of Inverness Airport [Station] on RailScot